Saturday, January 12, 2008

Crew Schedule

Hi All,

I'm just going to post a schedule for the crew assuming it will be easier that way. The next designer call is on February 7th. Beginning on Feb. 9th (tech), all of the crew must be at the rehearsals. For the production meetings and the run throughs, at least one person from each crew (designer or asst. designer) needs to be there
Any conflicts, please let me know ASAP.


Thurs. 2-7
3:00 - 6:00
TITUS
Run Show with Props
Cast and Crew Heads

6:00 - 7:00
TITUS
Production Meeting
Technical Crew Heads

Fri. 2-8
2:30 - 6:00
TITUS
Run Show with Props
Cast and Crew Heads

Sat. 2-9
9:00 - 9:00
TITUS
Technical Rehearsal
Dry Tech
All Technical Staff

Sun. 2-10
12:00 - 9:00
TITUS
Technical Rehearsal
Add Techical Elements to Play
Cast and Crew

Mon. 2-11
2:30 - 8:00
TITUS
1st Dress
Add Costumes
Cast and Crew

Tues. 2-12
5:00 - 10:00
TITUS
2nd Dress
Add Make-up
Cast and Crew

Wed. 2-13
5:00 - 10:00
TITUS
Final Dress
Final Run
Cast and Crew

Thurs. 2-14
5:30 - 10:00
TITUS
Performance (7:30)
Confirmed Date
Cast and Crew

Fri. 2-15
5:30 - 10:00
TITUS
Performance (7:30)
Confirmed Date
Cast and Crew

Sat. 2-16
5:30 - 10:00
TITUS
Performance (7:30)
Confirmed Date
Cast and Crew

Sun. 2-17
12:00 - 5:00
TITUS
Strike
Strike the Set and All Items
Cast and Crew